The flat rate pricing formula

Cost = hours × true labor cost + parts + extras · Price = cost ÷ (1 − margin), rounded up to the next $5

Margin is figured on the selling price, so a 60% margin means 60% of the ticket is gross profit after labor, parts and per-job extras. The effective rate per labor hour shows what the task really bills per hour once parts are taken out, a quick check against your market.

Flat rate pricing examples

These run the calculator's formula on example inputs: a true labor cost of $75 per hour, $25 of per-job extras and a 60% target margin. The hours and parts costs are placeholders, not market prices. Put in your own labor cost, your average times and what you actually pay for parts, because the price only means something with your numbers in it.

Task (example inputs)HoursParts costJob costPrice at 60%Bills per labor hour
Replace toilet fill valve and flapper0.75$30$111$280$331
Replace angle stop and supply line0.75$25$106$270$321
Replace kitchen faucet1.5$150$288$720$379
Replace water heater relief valve0.5$20$83$210$373
Replace garbage disposal (customer supplied)0.75$45$126$320$361
Replace pressure reducing valve2$250$425$1065$406

Two things the examples show: small parts jobs carry a high effective hourly rate because the trip and setup are built in, and the margin is on the whole ticket, so expensive parts raise the price a lot at the same margin. If you want a lower margin on high-dollar parts, set it on purpose for those tasks instead of letting one margin cover everything.

Worked examples, step by step

Example arithmetic only, using the same placeholder inputs as the table above ($75 per hour true labor cost, $25 extras, 60% margin). These are not real or recommended prices.

  1. Replace toilet fill valve and flapper: labor 0.75 h × $75 = $56.25; plus parts $30 and extras $25 = job cost $111.25. Price = $111.25 ÷ (1 − 0.60) = $278.13, rounded up to $280. Gross profit $168.75.
  2. Replace kitchen faucet: labor 1.5 h × $75 = $112.50; plus parts $150 and extras $25 = job cost $287.50. Price = $287.50 ÷ (1 − 0.60) = $718.75, rounded up to $720. Gross profit $432.50.
  3. Replace pressure reducing valve: labor 2 h × $75 = $150; plus parts $250 and extras $25 = job cost $425. Price = $425 ÷ (1 − 0.60) = $1,062.50, rounded up to $1,065. Gross profit $640.

Margin versus markup: a 60% margin means dividing cost by 0.4, which is the same as a 150% markup on cost. To find the labor cost to start from, use the break-even labor rate calculator.

Finding your true labor cost

  • Add a tech's yearly wages, payroll taxes, workers' comp, benefits and training.
  • Add the truck (payment, fuel, insurance, maintenance) and a fair share of office overhead.
  • Divide by billable hours, not hours paid. Drive time, shop time and callbacks aren't billable.

Building the price book

  • Use average times from your own job history where you can, not best-case times.
  • Re-price when parts, wages or fuel move. Many shops review the book twice a year.
Prices set. Now fill the schedule.

90 Leads, which publishes Plumbing Cheat Sheet, helps plumbing contractors book more of the jobs they want with Google, ads and call tracking.

Related tools

Estimates for planning only, not financial or tax advice. Found a problem with this tool? Tell us.